A region is looking for a specific developer to develop
a Battery Energy Storage System (BESS).
Project Features:
Installation capacity: 9,900 kVA import / 9,900 kW export
Grid connection: 33kV overhead line (Scottish Hydro Electric Power Distribution PLC)
Connection date (expected): October 31, 2027
Build-Operate model: The developer will be responsible for design, construction, and operation
Lease term: 20–40 years + revenue sharing and option fee payment